Bonneville Dam construction album, 1930s

Fishway bridge, 1936, Bonneville dam construction album, PH203_20Collection number: PH203_20

Extent: .1 linear ft. (1 volume)

Abstract

Album documenting construction of Bonneville Dam, 1930s. Images by R.W. Oliver and Bichel; most unsigned. Shows housing, equipment, excavation, construction, spillways. Some workers named.

Images shown: Fishway bridge, 1936. Bonneville Dam construction album, PH203_20, Special Collections and University Archives, University of Oregon, Eugene, Oregon 97403-1299. All rights reserved.

Access restrictions: None.

Publication rights: Property rights reside with Special Collections and University Archives. Copyright resides with the creators of the documents or their heirs. All requests for permission to publish images must be submitted to the Photographs Curator of Special Collections and University Archives. The reader must also obtain permission of the copyright holder.

Images:

  • PH203_20_001: Bonneville Dam Area 5-1-1934. [Panoramic of Bonneville dam area.] Date: 1934 May 1. By: Oliver, R.W. Loc: Columbia River
  • PH203_20_002: Overlooking Bonneville Dam Area 6-24-1934. [Panoramic of Bonneville dam area.] Date: 1934 Jun 24. By: Oliver, R.W. Loc: Columbia River
  • PH203_20_003: Spillway Dam Bonneville. [Panoramic of Spillway dam construction.] Date: 1935 Aug 2. By: Oliver, R.W. Loc: Columbia River
  • PH203_20_004: Bonneville Residence Area 10-15-35. [Panoramic of residential area, hills in background.] Date: 1935 Oct 13. By: Oliver, R.W. Loc: Columbia River
  • PH203_20_005: Entrance to Dam Reservation. [Bridge over roadway. Sign reads "Federal Public Works Bonneville Dam Project no.28.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_006: Bonneville Center or Community Center Post Office on this end. [Buildings behind trees, man and cars in roadway.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_007: Tractor on high line Sept. 1935. [tractor on high line being moved during construction.] Date: 1935 Sep. By: Unknown. Loc: Columbia River
  • PH203_20_008: [tractor on high line being moved during construction.] Date: 1935 Sep. By: Unknown. Loc: Columbia
  • PH203_20_009: Entrance to Dam Reservation from Co. River Highway. [Bridge over roadway, seen from side of road Sign reads "Federal Public Works Bonneville Dam Project no.28.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_010: 2nd to this end in bunkhouse where I stayed 1 mo. 20 beds in each? Aug. 17-Sept 14 1935. [Bunkhouses with Jeeps parked in front along street.] Date: 1935 Aug-Sep. By: Unknown. Loc: Columbia River
  • PH203_20_011: Pay Office Columbia Const. Co. [2 story offices.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_012: Back of Safeway store facing highway. [Backside of buildings in snow.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_013: 25-35 Cu Yds dirt- 16 wheels- each tire $250. [Large container of dirt set on top 16 tires. Man with back to camera.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_014: [tractor pulling 16 wheeled dirt container, being filled by scoop on high wire.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_015: [Construction of dam.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_016: [Construction of dam.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_017: [Construction of dam.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_018: [Construction of dam.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_019: Solid Pour on bedrock with inspection tunnels shown. Taken about Nov.1, 1935. [construction of dam, with high wire visible.] Date: 1935 Nov 1. By: Bichel. Loc: Columbia River
  • PH203_20_020: Bonneville Spillway Dam 10-15-35. [Panorama construction of spillway dam.] Date: 1935 Oct 15. By: Oliver, R.W. Loc: Columbia River
  • PH203_20_021: North Bonneville Wash. [Tail tower above houses.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_022: Tool house. [Signs on building read "Pipe Shop" Work Shop" "Tool Room" "Stretcher in Tool Room" "Important All men quitting or laid off must first check out at the field office".] Date: c. 1936. By: Unknown. Loc: Columbia
  • PH203_20_023: Tool house abt 36 tons carried around by high line (2 hi lines working together). [Tool shop building.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_024: one of two moving head towers of hi-line 90' high- cable +3"dia. [High line and building underneath, man standing on tracks leading to building.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_025: Piers rising from foundation block. [construction of spillway dam.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_026: Constructing Spillway Bonneville Dam Ore-Wash. [construction of spillway dam.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_028: [Workers working with rebar during construction of spillway.] Date: c. 1936. By: Unknown. Loc: Columbia
  • PH203_20_029: Constructing Spillway Bonneville Dam Ore-Wash. [Workers working with rebar during construction of spillway.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_030: Constructing Spillway Bonneville Dam Ore-Wash. [close-up of tunnels being constructed.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_031: Constructing Spillway Bonneville Dam Ore-Wash. [tunnels being constructed.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_032: taken March 19, 1936. [Workers sawing timber for dam construction.] Date: 1936 Mar 19. By: Unknown. Loc: Columbia River
  • PH203_20_033: [Bonneville residence area, from hillside.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_034: [Backsides of buildings, in residence area.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_035: Bonneville Spillway dam 3-15-36. [Panoramic of construction of spillway.] Date: 1936 Mar 15. By: Oliver, R.W. Loc: Columbia River
  • PH203_20_036: Taken March 19, 1936. Cofferdam blasted March 16, 1936 (2 tons powder) at 6:45 am. Cofferdam on East side of piers. [debris in water against berm. "Safety Counts" sign on background.] Date: 1936 Mar 19. By: Unknown. Loc: Columbia River
  • PH203_20_037: Tanner Creek Falls at Bonneville. [ice covered waterfall.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_038: Taken April 1, 1936 at Bonneville Dam bunk-houses. Mt. Murna in background. [Man walking across snow covered parking lot. Sign on store in background "National Commissary Co. Inc.".] Date: 1936 Apr 1. By: Unknown. Loc: Columbia River
  • PH203_20_039: Feb 1, 1937 6' snow winter at Bonneville. [Snow covered parking lot. Sign in background reads " Outdoor shoes. Nudelman Bros. Union made work clothing".] Date: 1937 Feb 1. By: Unknown. Loc: Columbia River
  • PH203_20_040: Spillway, Bonneville Dam, Power House. 4-13-36 Oliver 53. [Panorama of construction of Bonneville Dam. Sign on crane reads "Washington Iron Works".] Date: 1936 Apr 13. By: Oliver, R.W. Loc: Columbia River
  • PH203_20_041: Bonneville Dam Spillway April 6, 1936. [Construction of Spillway. View from water of spillway with water flowing through unfinished parts.] Date: 1936 Apr 6. By: Unknown. Loc: Columbia River
  • PH203_20_042: [Snow covered trees.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_043: Engineer's house's. $25,000 houses. [Complex of houses on dirt, next to Columbia River.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_044: Mona Bell Hill's house. Worked 3 weeks there. May 1935. [House on hillside surrounded by fir trees.] Date: 1935 May. By: Unknown. Loc: Columbia River
  • PH203_20_045: Taken Feb. 1936 Temp 10-20 degrees at cave on Tanner Creek. Men-2 workers at Bonneville Dam. [Man with pipe and man with rifle standing in front of ice covered cave.] Date: 1936 Feb. By: Unknown. Loc: Columbia
  • PH203_20_046: Woods around shack at Bonneville looking out one window. [snow covered trees.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_047: Bonneville Dam Spillway. April 6, 1936. [Men working on spillway construction, before concrete was poured.] Date: 1936 Apr 6. By: Unknown. Loc: Columbia River
  • PH203_20_048: Bonneville Dam Spillway. April 6, 1936. [Men working on spillway construction, before concrete was poured, snowcapped hills in background.] Date: 1936 Apr 6. By: Unknown. Loc: Columbia River
  • PH203_20_049: [Construction of Spillway with water flowing through.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_050: [Construction of Spillway, men working with wood forms.] Date: c. 1936. By: Unknown. Loc: Columbia
  • PH203_20_051: Bonneville Dam 4-29-36 Oliver 55. [Panorama of water flowing through construction of Spillway.] Date: 1936 Apr 29. By: Oliver, R.W. Loc: Columbia River
  • PH203_20_052: 5-May-36. [Construction of Power House.] Date: 1936 May 5. By: Unknown. Loc: Columbia River
  • PH203_20_053: 5-May-36. [Construction of Power House.] Date: 1936 May 5. By: Unknown. Loc: Columbia River
  • PH203_20_054: May 1936 High Water Period. [Water flooding construction area, wood floating in water.] Date: 1936 May. By: Unknown. Loc: Columbia River
  • PH203_20_055: My Cabin. [small wood cabin surrounded by snow.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_056: Our crew working on Fishway Bridge May 1936. [Sandbags on ground in front of construction of Fishway bridge.] Date: 1936 May. By: Unknown. Loc: Columbia River
  • PH203_20_057: 1936 Summer trip up Col. To Bonneville. [Sternwheeler headed up Columbia with passengers on board.] Date: 1936. By: Unknown. Loc: Columbia River
  • PH203_20_058: [Two women standing reading newspaper, presumably on sternwheeler.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_059: Spillway Bonneville Dam 5-8-36 Oliver 57. [Panorama of construction of Spillway. Includes high wire.] Date: 1936 May 8. By: Oliver, R.W. Loc: Columbia River
  • PH203_20_060: May-36. [Two men in suits on walkway looking down at construction.] Date: 1936 May. By: Unknown. Loc: Columbia River
  • PH203_20_061: Inside of Cabin. [work area inside of cabin, includes hand saws, books, apple and other equipment.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_062: Cabin at Bonneville on hillside. [Snow covered cabin seen through trees.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_063: Spillway Bonneville Dam 6-12-36. 58. [Panorama of construction of spillway, includes high wire.] Date: 1936 Jun 12. By: Unknown. Loc: Columbia River
  • PH203_20_064: Taken about Aug. 10, 1936. [Construction of dam, with water flowing through, high wire visible.] Date: 1936 Aug 10. By: Unknown. Loc: Columbia River
  • PH203_20_065: false work of Fishway bridge between pier 17 & 18. Our crew put in bridge. [Construction of Fishway Bridge.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_066: Bonneville Icicles Feb. 1936. [Icicles on tree branch.] Date: 1936 Feb. By: Unknown. Loc: Columbia
  • PH203_20_067: Before last pour on 85 ft. deck on South side. [Elmer, Walt Johnson and Bill standing on concrete forms.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_068: Taken about Aug. 10, 1936. [Construction of dam, with water flowing through, high wire visible, group of men standing near tool house.] Date: 1936 Aug 10. By: Unknown. Loc: Columbia River
  • PH203_20_069: 10-Aug-36. [Construction of Spillway.] Date: 1936 Aug 10. By: Unknown. Loc: Columbia River
  • PH203_20_070: [Close-up of construction of spillway.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_071: [Close-up of construction of spillway.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_072: Downstream cribbing north side. [Construction of dirt roadway over water.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_073: [Close-up of construction of spillway, with high wire visible.] Date: c. 1936. By: Unknown. Loc: Columbia
  • PH203_20_074: Upstream Cofferdam cribbing North side. [Construction of Cofferdam .] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_075: 85' deck So. Side. [Fred Brandt, Ralph and Joe working on deck.] Date: c. 1936. By: Unknown. Loc: Columbia
  • PH203_20_076: [Construction of Spillway.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_077: Constructing Spillway Bonneville Dam Ore-Wash. [construction of spillway, with high line visible.] Date: 1936 Aug 10. By: Unknown. Loc: Columbia River
  • PH203_20_078: U/S Cofferdam Aug 1936. [Construction of Cofferdam .] Date: 1936 Aug. By: Unknown. Loc: Columbia River
  • PH203_20_079: Last Crib of Downstream Cofferdam Aug 1936. [Construction of Cofferdam .] Date: 1936 Aug. By: Unknown. Loc: Columbia River
  • PH203_20_080: 12-Aug-36. [Construction of spillway.] Date: 1936 Aug 12. By: Unknown. Loc: Columbia River
  • PH203_20_082: 61 8-18-36 Bonneville Dam. [Panorama of men working on dam construction, on area between 2 berms.] Date: 1936 Aug 18. By: Unknown. Loc: Columbia River
  • PH203_20_083: [Construction of Spillway, dug out area beside completed supports.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_084: Bonneville Dam Ore-Wash. [Construction on top of supports.] Date: c. 1936. By: Unknown. Loc: Columbia
  • PH203_20_085: [Highline tower.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_086: [Man standing on top of dam construction. Columbia in background.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_087: [Men digging dirt behind wall.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_088: [Scooper filling dump truck while in water.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_089: [Construction of dam.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_090: [Cabin.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_091: North Unit Spillway Bonneville Dam. [Panorama of construction of spillway.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_092: [Water flowing through construction of spillway.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_093: Spillway Bonneville Dam 11-1-36. [Panorama of Spillway construction.] Date: 1936 Nov 1. By: Unknown. Loc: Columbia River
  • PH203_20_094: North Unit Spillway Bonneville Dam 11-1-36 66. [Panorama of Spillway construction.] Date: 1936 Nov 1. By: Unknown. Loc: Columbia River
  • PH203_20_095: Spillway Bonneville Dam 1-1-37 67. [Panorama of Spillway construction.] Date: 1937 Nov 1. By: Unknown. Loc: Columbia River
  • PH203_20_096: Spillway Bonneville Dam 1-1-37 67. [Panorama of Spillway construction.] Date: 1937 Nov 1. By: Unknown. Loc: Columbia River
  • PH203_20_097: Constructing Spillway Bonneville Dam Ore-Wash. [Construction of spillway.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_098: Constructing Spillway Bonneville Dam Ore-Wash. [Construction of spillway.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_099: [Close-up of supports of spillway.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_100: Bonneville excursion trip boats at dam 1936. [Passengers exiting sternwheeler "Cascades" and "Northwestern".] Date: 1936. By: Unknown. Loc: Columbia River
  • PH203_20_101: Constructing Spillway Bonneville Dam Ore-Wash. [Construction of spillway.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_102: Bonneville Dam 4-24-37 71. [Panorama of Construction of support beams.] Date: 1937 Apr 24. By: Oliver, R.W. Loc: Columbia River
  • PH203_20_103: 15-340 Power House Bonneville dam. [Up stream power house.] Date: c. 1936. By: Unknown. Loc: Columbia
  • PH203_20_104: Powerhouse down stream. [Down stream power house.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_105: Bonneville project on the Columbia river-61. [looking down on Bonneville dam and spillway.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_106: [Power station downstream before being surrounded by water.] Date: c. 1936. By: Unknown. Loc: Columbia
  • PH203_20_107: [Power station downstream before being surrounded by water.] Date: c. 1936. By: Unknown. Loc: Columbia
  • PH203_20_108: Aug. 1935. [Power station upstream, before being surrounded by water.] Date: 1935 Aug. By: Unknown. Loc: Columbia River
  • PH203_20_109: [Power station upstream, before being surrounded by water.] Date: c. 1936. By: Unknown. Loc: Columbia
  • PH203_20_110: [Construction of dam from a distance.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_111: [Interior construction of dam.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_112: [Construction with high wire with wet concrete being moved.] Date: c. 1936. By: Unknown. Loc: Columbia
  • PH203_20_113: [Construction of dam & forms for concrete.] Date: c. 1936. By: Unknown. Loc: Columbia River
  • PH203_20_114: [construction of fish ladder.] Date: c. 1936. By: Unknown. Loc: Columbia River

Preferred citation: [Identification of item], Bonneville Dam construction album, PH203_20-[image number], Special Collections and University Archives, University of Oregon, Eugene, Oregon 97403-1299.

Processed by: Normandy S. Helmer

Date Completed: Oct. 2006

Maintained by: N. Helmer, spcarref@uoregon.edu
Last Modified: 10/26/2006