UO Libraries Home Page

Knight Library: 1st Shift

  • December 19, 1992 through January 3, 1993
  • Library Closed to patrons, materials paged
  • Collections/Work areas:
What:From:To:# sections shelving needed
General Collection 3rd floor 5th Level not calculated in same way
Documents collection 2nd Floor 1st Floor South: perm. loc
  • 110 df, 10" 14/section
  • 95 df, 10", 14/section, slotted
  • 61 df, 10", 16/section, slotted
  • 9 df, 10", 12/section, slotted, 84"
  • 7 sf, 10", 3 section counter-top arranged into 5 section blocks
  • 2 sf, 10", 7/section
  • a whole bunch of compact shelving
Catalog Dept. collections 1st Floor 4th Floor temp loc 100 df, 10", 14/section
Serials Dept. collections 1st Floor 1st Floor West (perm loc)
  • 3 sf, 10", 7/section
  • 3 df, 10", 14/section
Acquisitions & Coll Dev. Depts. collections 1st Floor and Ground Floor 4th Floor, temp loc
  • 35 sf, 10", 7/section
Holding Room ??? 1st Floor West, perm. loc
  • 3df, 10", 14/section
  • 3sf, 10", 7/section
Reference collection 1st Floor 2nd Floor south, temp. loc
  • 109 df, 10", 14/sect
  • need 50 pull-out shelves
Microforms collection 3rd floor 1st Floor south, perm. loc
  • 94 df, 10", 16/sect
  • 46 sf, 10", 8/sect
  • 3 df, 10", 14/sect, 84" high
  • 3 sf, 10", 7/sect, 84" high
Microfilm Project Dungeon Forgot where it moved temporarily
  • 55 sf, 18", 5/sect or
  • 25 df, 18", 10/sect
  • 10 sections, 36-40", with two shelves below
Douglass Listening Room collection 3rd Floor 2nd Floor (where Documents was) 20 df, 12" wide (12 slotted with backs), 90" tall

Staffing needs for the 3to5 (3rd floor to 5th Level) Shift:

Assume that all ranges on the 5th Level are already constructed and spanned.

 

  • 1.25 team hours per df section (includes shelfreading, travel time, loading, unloading, making end cards)
  • one team hour = five staff hours
  • 1335 sections x 1.25 team hrs = 1,669 team hours
  • 1,669 team hours x 5 staff = 8,345 staff hours
  • 1,669 team hours divided by two weeks = 835 team hrs/week
  • 835 team hours divided by 7 days = 120 team hrs/day
  • 120 team hours x 5 staff = 600 staff hrs/day
  • 600 staff hours divided by 8 hours/day for one person = 75 people/day, each working 8 full hours
  • 75 people divided by 5 people/team = 15 start points
  • 120 team hrs divided by 4 hr shifts= 30 shifts (4 hr ea, 5 people ea per day)
    • 6-10a: 7.5 teams
    • 10a-2p: 7.5 teams
    • 2-6p: 7.5 teams
    • 6-10p: 7.5 teams
  • Why we think 1.25 hrs/df section is right: This summer we shifted and found that our rate was 1df section per hour with 2.5 people. The beginning and end points were very close: no elevators, no bottle-necks, no integrating collections from other areas, no shelfing reading, and no novice shelvers. Pad that number to account for all those elements which will be present in this shift.